The Early Vision (2000’s)

Identifying the Need for a New Clubhouse

The need for a new patrol base and clubhouse was identified in the early 2000s as the Club grew and expanded its services across the wider North Shore. By 2009, the Club had developed concept plans (see above banner) for a new facility with support from the North Shore City Council. However, progress was halted with the Super City merger in 2010, which triggered the requirement to develop a Reserve Management Plan (RMP) for the Mairangi Bay Beach Reserve under the Reserves Act 1977.

The Super City Merger and the Reserve Management Plan (2010–2015)

Reshaping the Process and New Planning Requirements

Between 2011 and 2015, Auckland Council worked through the reserve management planning process, and in 2015 the RMP was approved by the Hibiscus and Bays Local Board. The Plan allowed the Club to rebuild on its existing site, with additional storage contemplated both beneath the clubhouse and across Sidmouth Street within the reserve.

During this time, the Club continued to grow, necessitating the increased use of temporary storage containers for lifesaving equipment, which were placed around the Sidmouth Reserve.

Growth, Temporary Solutions, and Coastal Challenges (2015–2016)

Expansion, Storage Issues, and Coastal Risk Assessments

Concerns about the strength of the existing seawall and future maintenance costs prompted Auckland Council to commission a coastal hazard assessment. This assessment found that the Club’s current location was unsuitable for redevelopment due to coastal erosion risks.

Uncertainty and Advocacy (2016–2019)

Pushing for Clarity Amid Council Delays

Between 2016 and 2019, the Club was left in a state of limbo, with Auckland Council and the Local Board unable to agree on a way forward. During this period, the Club repeatedly lobbied for clarity, eventually resulting in another coastal hazard assessment in 2019.

This second report outlined coastal erosion susceptibility zones and proposed a number of options, recommending that the seawall be gradually removed and the coastal edge naturalised into dunes.

Although a review of the 2015 Reserve Management Plan was agreed to in principle, further delays occurred due to the COVID-19 pandemic and Watercare’s redevelopment project at Mairangi Bay.

New Opportunities and New Challenges (2019–2022)

Watercare’s Project, Storage Relocation, and COVID-19 Disruptions

Watercare’s project required the removal of the Club’s old storage shed but created an opportunity to repurpose the vacated land for long-term equipment storage.

In alignment with the two-footprint strategy outlined in the 2015 RMP, the Club’s planning focused on rebuilding a new clubhouse east of Watercare’s new facility, closer to Sidmouth Street. This was based on the assumption that the road frontage would eventually be removed, as contemplated by the 2015 RMP.

A Fresh Start: Reserve Management Plan Review (2023)

Local Board Support and Community Consultation

In 2023, the Local Board finally approved funding for a full review of the Reserve Management Plan, and public consultation commenced later that year.

Key results from the survey included:

  • 67% of respondents supported retaining the seawall;

  • The majority of respondents supported the Club remaining within the Reserve.

 

Finding a Home: Site Constraints and Final Proposal (2024)

Determining the Future Location of MBSLSC

During 2024, Auckland Council engaged the Club to further understand its operational requirements and preferred locations. Council also consulted with key stakeholders, including local iwi, and engaged WSP to develop an overall reserve concept plan identifying several potential surf lifesaving club locations.

Following specialist site constraint assessments, only one location — at the northern end of the reserve — was identified as suitable and free of significant risks for a future Mairangi Bay Surf Lifesaving Club facility.

Clubhouse Re-Development: Next Chapter

Milestone Achieved — Footprint Allocated

We are pleased to confirm that the Hibiscus and Bays Local Board / Auckland Council has formally approved, via the 2025 Reserve Management Plan, a location for MBSLSC’s future surf lifesaving facility in the northern end of the reserve. This can accommodate a 600 m² building footprint which is envisaged to accommodate all operational activities, including storage. This represents the culmination of a lengthy RMP and site-constraint process, and a major step forward in securing our long-term future at Mairangi Bay.

What Happens Now — Project Timeline

With footprint secured, we’re commencing the redevelopment process, which is expected to span 3–5 years. The stages will include:

  • A feasibility study 

  • Architectural and structural design, followed by resource consent submissions

  • Construction, with the objective of delivering a modern, fit-for-purpose clubhouse that meets current and future needs

Commitment to Transparency & Community Updates

As we progress, concept designs, plans, and updates will be posted on this page as they are confirmed, so our members, supporters and the local community can stay informed every step of the way.

Our Vision — Serving Generations to Come

This new facility will enable MBSLSC to continue delivering lifesaving services, surf-sport training, junior surf programs, and community engagement, in a safe, sustainable environment that honours our heritage and embraces the future.